(A) Periodic inspections during the installation of improvements shall be made by city to insure conformity with the approved plans and specifications as contained in the subdivider’s contract. The subdivider shall notify the proper administrative officials when each phase of the improvement is ready for inspection. Upon acceptable completion of installation of the required improvements, the city shall issue a letter to the subdivider or his or her agent, and such letter shall be sufficient evidence for the release by the city of the portion of the surety bond, certified check or cash deposit as designated in the subdivider’s contract for the completed improvement.
(B) When the engineer, following inspection of a subdivision, certifies to the Council that all improvements have been constructed in accordance with city specification, the Council may proceed to accept the facilities for which bond has been posted.
(Ord. passed 7-21-99)