8-5-19: AS BUILT PLANS:
All applicants are required to submit actual as built plans for any stormwater management practices located on site after final construction is completed. The plan must show the final design specifications for all stormwater management facilities and must be certified by a professional engineer. A final inspection by the public works department is required before the release of any performance securities can occur. (Ord. 2016-12, 8-16-2016)