8-5-18: FIELD INSPECTIONS:
   A.   Field inspections during preconstruction and construction shall be conducted by the public works department or other designated agent as outlined in the inspection checklist provided by the public works department.
   B.   Final approval inspections will be conducted by both the public works department (for SWPPP completion and notice of termination for the stormwater permit) and the engineering department (for final acceptance of stormwater facilities).
   C.   Access onto private property is authorized for the city engineer, the public works director, or other designated qualified personnel to inspect construction stormwater BMPs on private properties that discharge to the city stormwater system.
   D.   Access onto private properties that discharge to the city stormwater system is authorized for the public works director to inspect existing stormwater facilities to ensure proper function and maintenance on an annual basis. (Ord. 2016-12, 8-16-2016)