§ 156.285 PERMIT REQUIREMENTS, EXCEPTIONS, APPLICATION FORMS AND FEES.
   (A)   Anyone wishing to erect, construct, reconstruct, repair, or establish any building, transmission line, communication line, pole, tower, smokestack, chimney, wires, or other structure or appurtenance thereto of any kind or character; or to plant or replant any tree or other object of natural growth which, when mature, would violate the requirements of § 156.282 above, within the Airport Hazard Area must first obtain a permit from Zoning Administrator.
   (B)   Exception. Within the turning zones, no permit shall be required for any construction, reconstruction, repair, or planting of anything which, when completed, or, in the case of natural growth, when mature, does not exceed 75 feet above the nearest existing or proposed runway end.
   (C)   Application form. Application for a permit as required under these regulations shall be made on a form to be available in the office of the Zoning Administrator and shall indicate the approximate location, ground elevation with reference to the end of the nearest runway or landing strip and height of the proposed structure or planting (mean sea level elevation).
   (D)   Permit fee. The fee for each permit issued shall be established by the City Council as indicated on the fee schedule annually adopted by the City Council.
(Ord. 3887, passed 1-21-2014)