§ 155.552 IMPROVEMENT PROCEDURES.
   Improvements installed by a developer for any land division, either as a requirement of these regulations or at his or her own option, shall conform to the requirements of this chapter and improvement standards and specifications adopted by the city, and shall be installed in accordance with the following procedure.
   (A)   Improvement work shall not be commenced until plans have been checked for adequacy and approved by the city. Plans shall be prepared in accordance with requirements of the city.
   (B)   Improvement work shall not be commenced until the city has been notified in advance; and, if work has been discontinued for any reason, it shall not be resumed until the city has been notified.
   (C)   Improvements shall be constructed under the inspection and to the satisfaction of the city. The city may require changes in typical sections and details in the public interest, if unusual conditions arise during construction to warrant the change.
   (D)   All underground utilities, sanitary sewers and storm drains installed in streets by the subdivider shall be constructed prior to the surfacing of the streets. Stubs for service connections for underground utilities and sanitary sewers shall be placed to a length eliminating the necessity for disturbing the street improvements when service connections are made.
   (E)   A map showing all public improvements as built shall be filed with the city upon completion of the improvements.
(Prior Code, § 16.125.30) (Ord. 427, passed 5-16-2016)