§ 155.011 FINAL ACTION ON PERMIT APPLICATION WITHIN 120 DAYS.
   (A)   Pursuant to ORS 227.178, the city shall complete final action on permit applications, including resolution of all appeals within 120 days of receipt of a complete application. This time requirement shall not apply to legislative decisions. The determination of completeness shall be made by the city. The 120- day time limit may be waived in writing by the applicant.
   (B)   In computing any period of time prescribed or allowed by this section, the day or event from which the designated period of time begins to run shall not be included. The last day of the period so computed shall be included unless it is a Saturday, Sunday or legal holiday, in which event the period runs until the next day which is not a Saturday, Sunday or legal holiday.
(Prior Code, § 16.00.090) (Ord. 460, passed 6-3-2019)