1155.09   SEDIMENT AND EROSION CONTROL.
   (a)    Erosion Control Plan:
      (1)    Measures shall be taken to minimize erosion and its impacts during subdivision construction activity.
      (2)    All construction and improvement activity areas including but not limited to berms, ditches, streams, retention areas, and slopes shall be protected against soil erosion by seeding within 15 days of the completion of such activity. In the interim, mechanical methods such as mulch, silt fencing, and temporary seeding shall cover and contain all exposed areas throughout the site during construction and prior to seeding.
      (3)    Detailed Erosion Control Plans set forth the techniques to be used both temporarily (during construction) and permanently and a schedule for implementing or installing same shall be submitted to Lake County Soil and Water Conservation District for review and recommendation. Evidence that the plans for same meet or exceed Lake County Soil and Water Conservation Department regulations, Lake County Engineering requirements, and North Perry Village Regulations, shall be submitted to the Planning Commission for approval of the final plat.
      (4)    All erosion control devices shall be in place and maintained at the start of construction and other measures shall be implemented.
      (5)    Erosion control plans shall be based upon controlling erosion on-site with the object of eliminating or minimizing erosion or sedimentation impacts off-site. Techniques, devices or measures used shall meet or exceed Village Regulations and shall be as approved by the Village Engineer based on current policies and standards.
      (6)    No construction shall proceed in streams, waterways, retention ponds, conservation areas or areas deemed to be retained as natural by the Planning Commission without an inspector reporting to the Village Engineer present.
      (7)    A bond to an amount satisfactory to cover all construction restoration and potential remediation shall be required. The amount of such bond shall meet or exceed the Village Engineer estimate of such construction and be to the satisfaction of the Village Solicitor.
   (b)    Erosion Control Schedule: A schedule for implementing, installing and inspecting of all erosion control measures shall be updated by the Village Engineer as work progresses.
   (c)    Penalties:
      (1)    The Zoning Inspector in consultation with the Village Engineer shall issue a stop work order for failure to maintain adequate erosion control measures or failure to maintain an erosion control schedule. Such penalty shall remain in effect until corrective measures are installed and functioning to the satisfaction of the Lake Soil and Water Conservation District and the Village Engineer.
      (2)    Additional financial penalties or remediation requirements may be imposed at the recommendation or direction of the Lake Soil and Water Conservation District and the Village.
         (Ord. 19-10.  Passed 11-7-19.)