(A) (1) Installation of waste water monitoring and/or flow measurement facilities necessary to inspect, monitor, sample, and test the amounts and characteristics of the waste water discharges may be required of any owner by the village.
(2) A plan for proposed monitoring and flow measurement facilities shall be submitted to the village for approval within 60 days of receipt of request for installation.
(3) The installation shall be completed within 90 days of the village approval.
(B) (1) Monitoring facilities and/or flow measurement facilities required by the village shall be constructed, operated, and maintained at no cost to the village.
(2) The entire facility shall be maintained at all times in a safe and proper operating condition by the person installing the facility and/or causing the discharge that is being monitored and/or measured.
(3) Access to the monitoring and/or flow measurement facilities shall be made available immediately to authorized representatives of the village at any time.
(4) Authorized representatives of the village shall have the right to and shall be provided with adequate space necessary to set up and operate additional monitoring equipment at such facilities.
(C) (1) The monitoring facility shall be located as to be readily accessible at all times to representatives of the village.
(2) Access shall not be obstructed by parked vehicles, supplies, or equipment or any other object or person which might prevent accessibility.
(Ord. 287, passed 3-12-2024) Penalty, see § 51.999