(a) Soil Disturbing Activities Submitting a Storm Water Pollution Prevention Plan. The applicant shall submit two sets of the SWP3 and the applicable fees to the Village and two sets of the SWP3 and the applicable fees to the Summit SWCD as follows:
(1) For subdivisions: After the approval of the preliminary plans and with submittal of the improvement plans.
(2) For other construction projects: Before issuance of a zoning permit by the Zoning and Building Inspector.
(3) For general clearing projects: Prior to issuance of a zoning permit by the Zoning and Building Inspector.
(b) The Village and the Summit SWCD shall review the plans submitted under division (a) of this section for conformance with this regulation and approve, or return for revisions with comments and recommendations for revisions. The Village shall review the plans submitted under this division (b) for conformance with this regulation and approve or return for revisions with comments and recommendations for revisions. A plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised plan.
(c) Soil-disturbing activities shall not begin and zoning permits shall not be issued without an approved SWP3.
(d) A pre-construction meeting must be held with the Summit SWCD inspector prior to earthwork activities. The applicant, contractor, and applicant's engineer should be in attendance at the pre-construction meeting.
(e) An SWP3 for individual sublots in a subdivision may not be approved unless the larger common plan of development or sale containing the sublot is in compliance with this regulation.
(f) Approvals issued in accordance with this regulation shall remain valid for two years from the date of approval.
(Ord. 2007-73. Passed 12-12-07.)