§ 51.38 INSPECTION OF CONSTRUCTION SITE.
   (A)   All construction sites involving LDA and requiring an approved ESCP shall be inspected and approved by a Compliance Officer at each stage of construction consistent with the seven stages set forth in this division (A). Compliance Officers shall inspect construction sites as authorized by this section and shall either approve that portion of the work completed or shall notify the person receiving approval for the LDA that the work is not in compliance with the approved ESCP. Plans for grading, stripping, excavating and filling work bearing the stamp of approval of a Compliance Officer shall be maintained at the construction site during all stages of the project. To obtain the required inspections for each stage of construction, the person receiving approval for the LDA shall notify the Public Works Department’s office at least two working days before each of the following stages:
      (1)   Installation of erosion and sediment control measures;
      (2)   Start of construction;
      (3)   Completion of site clearing and rough grading;
      (4)   Installation of any stormwater conveyance structures;
      (5)   Completion of final grading;
      (6)   Close of the construction season; and
      (7)   Completion of project.
   (B)   The person receiving approval for LDA and corresponding ESCP shall make regular inspections of all control measures in accordance with the inspection schedule outlined in the approved ESCP. The purpose of such inspections will be to determine the overall effectiveness of the ESCP and the potential need for additional control measures. All inspections shall be documented in writing and submitted to the Public Works Department’s office at the time intervals specified in the Stormwater Management Guidance Manual.
(Ord. passed 10-4-2016)