The Public Works Department’s office shall review each request for approval of LDA and the corresponding ESCP to determine conformance with the requirements of this subchapter. Within ten days after receiving a building permit application and corresponding ESCP, the Public Works Department’s office shall, in writing:
(A) Approve the requested LDA and corresponding ESCP;
(B) Approve the requested LDA and corresponding ESCP subject to conditions as may be necessary to satisfy the objectives of this subchapter; or
(C) Deny the requested LDA and corresponding ESCP, indicating the reason(s) for denial and the procedure for submitting a revised ESCP, if appropriate.
(Ord. passed 10-4-2016)