(a) No soil disturbing activities shall be permitted until a cash bond has been deposited with the Newton Falls Finance Department to the satisfaction of the Newton Falls Engineer sufficient for Newton Falls to perform the obligations otherwise to be performed by the owner of the development area as stated in this chapter and to allow all work to be performed as needed in the event that the applicant fails to comply with the provisions of this chapter. The cash bond shall be returned, less any Newton Falls administrative fees, after all work required by this chapter has been completed and final stabilization has been reached, all as determined by the Newton Falls Engineer.
(b) No project subject to this regulation shall commence without a SWP3 or Abbreviated SWP3 approved by the Newton Falls Engineer.
(Ord. 2005-09. Passed 4-4-05.)