1343.09 PERFORMANCE STANDARDS.
   The SWP3 must contain a description of the controls appropriate for each stage of construction operation and the applicant must implement such controls. BMP selection and design must meet criteria established within the current Construction General Permit. BMPs must be designed, constructed and installed to meet the specifications in Rainwater Land Development or another design manual acceptable to the Village. The approved SWP3, and the sediment and erosion controls, and non-sediment pollution controls contained therein, shall be implemented and maintained according to the requirements in the Construction General Permit. Site operators must conduct site inspections as described in the Construction General Permit.
   Certified inspection reports shall be submitted to the Village engineer within seven (7) working days from the inspection and retained at the development site.
   The following standards will also apply:
   (a)   Off-site tracking of sediment and dust control. Best management practices BMPs must be implemented to ensure sediment is not tracked off-site and that dust is controlled. These BMPs must include, but are not limited to, the following:
      (1)   Construction entrances shall be built and shall serve as the only permitted points of ingress and egress to the development area. These entrances shall be built of a stabilized pad of aggregate stone or recycled concrete or cement sized greater than 2" in diameter, placed over a geotextile. Culverts shall be provided where construction entrances cross drainage ditches and water bars shall be provided to divert sediment-laden runoff away from connected roadways.
      (2)   Streets and catch basins adjacent to construction entrances shall be kept free of sediment tracked off site. Streets directly adjacent to construction entrances and receiving traffic from the development area, shall be cleaned daily to remove sediment tracked off-site. If applicable, the catch basins on these streets nearest to the construction entrances shall also be cleaned weekly and protected from sediment-laden runoff, if feasible without posing a public safety hazard.
      (3)   Based on site conditions, the Village Engineer and/or the Mahoning County SWCD may require additional best management practices to control off site tracking and dust. These additional BMPs may include:
         A.   Fencing shall be installed around the perimeter of the development area to ensure that all vehicle traffic adheres to designated construction entrances.
         B.   Applicants shall take all necessary measures to comply with applicable regulations regarding fugitive dust emissions, including obtaining necessary permits for such emissions. The Village Engineer and/or the Mahoning County SWCD may require dust controls including the use of water trucks to wet disturbed areas, tarping stockpiles, temporary stabilization of disturbed areas, and regulation of the speed of vehicles on the site.
   (b)   Construction vehicles shall avoid water resources. If it is infeasible to provide and maintain an undisturbed natural buffer around water resources, the SWP3 shall comply with all the following additional requirements:
      (1)   All stream crossings shall be designed as specified in the most recent edition of Rainwater and Land Development.
      (2)   Temporary stream crossings shall be constructed if water resources or wetlands will be crossed by construction vehicles during construction.
      (3)   Construction of bridges, culverts, or sediment control structures shall not place soil, debris, or other particulate material into or close to the water resources or wetlands in such a manner that it may slough, slip, or erode.
      (4)   Protected areas or critical areas, including wetlands and riparian areas shall be physically marked in the field prior to earth disturbing activities.
   (c)   For sites that will not be completed by October 1, a Pre-Winter Stabilization Meeting shall be held by the landowner and the developer, engineer and contractor of the project and the Village prior to October 1, in order to plan and approve winter erosion and sediment controls as defined in the most current online edition of Rainwater and Land Development.
      (Ord. 2023-04. Passed 3-13-23.)