(a) Request for Final Inspection. The subdivider upon completion of all the improvements as required on the approved construction drawings, shall request in writing a final inspection by the County Engineer and/or Sanitary Engineer.
(b) Final Inspection. Upon written request, the County Engineer shall make a final inspection of all the improvements as required on the approved construction drawings. The County Sanitary Engineer, upon written request shall make a final inspection of all required sanitary improvements as shown on the approved construction drawings.
(c) Core Samples Required. Prior to final inspection approval, the developer shall show evidence of satisfactory pavement thickness by taking cores at locations determined by the County Engineer. Should any core show a deficiency in thickness of more than one-half inch, the procedure outlined in the current Ohio Department of Transportation's "Construction and Materials Specifications" will be used to make necessary corrections.
(d) Temporary Maintenance Guarantee. The subdivider shall maintain all improvements for one year after completion as determined by the inspection of the County Engineer. Maintenance shall be guaranteed by the posting of a maintenance bond or some other suitable instrument as approved by the Planning Commission. The amount of the guarantee shall be equal to ten percent (10%) of the total estimated cost of all improvements as shown on the approved construction drawings. The minimum amount of bond shall not be less than one thousand dollars ($1,000).
(Ord. 88-1. Passed 6-23-88.)