1109.09 INSPECTION.
   Inspection shall be required for all improvements as shown on the approved construction drawings.
   (a)   Responsible Officials.
      (1)   The official responsible for the inspection of all improvements (street, storm sewer/retention, sedimentation, etc.) as shown on the approved construction drawings shall be the County Engineer. The official responsible for the inspection of all sanitary sewers shall be the County Sanitary Engineer.
      (2)   The Township Road Superintendent or Supervisor and Subdivider's Engineer shall be involved in the final inspection and sign same.
      Note:   The subdivider's engineer and Township Road Superintendent shall work out a suitable inspection schedule with the County Engineer or Sanitary Engineer in order to assist on inspections during the various phases of development.
   (b)   Inspection Fees. All inspection fees shall be paid for by the subdivider as determined by the County Engineer and Sanitary Engineer.
   (c)   Notification Required Prior to Start of Construction. The subdivider shall notify the County Engineer and/or the Sanitary Engineer three days prior to the start of construction in order to establish an inspection schedule.
      (Ord. 88-1. Passed 6-23-88.)