1109.08 GUARANTEE FOR INSTALLATION OF IMPROVEMENTS.
   All improvements required herein shall be constructed prior to the recording of the final plat; or the subdivider shall furnish the Commission with a subdivision bond, cash escrow or letter of credit or some other suitable instrument as approved by the Commission covering one-hundred percent (100%) of the total cost of all improvements as shown on the approved construction drawings.
   Note: All improvements contained within a recorded final plat shall be completed within two years, unless an extension of time is granted by the Commission.
   (a)   Construction Cost Estimate. The estimate of cost of all improvements shall be prepared by the subdivider's engineer and shall be subject to review and approval by the County Engineer. The request for cost approval shall be submitted in writing to the County Engineer with a copy also being submitted in the Planning Office.
      (Ord. 88-1. Passed 6-23-88.)