1122.04 PROCEDURE.
   (a)   An applicant proposing a development subject to Site Plan Review under this Chapter shall file with the Zoning Commissioner, ten (10) copies each of the site plan documents required according to Section 1122.10, along with the required application fee.
   (b)   For developments that involve one (1) or more conditional uses and also requires site plan approval in accordance with this Chapter, the Planning and Zoning Commission retains authority to grant approval for bid requirements. Approval for both conditional uses and for site plan review may be granted concurrently and in accordance with the requirements of this Chapter.
   (c)   After reviewing the application for completeness and determining that the application is complete, the Zoning Commissioner shall transmit copies of the application to the Planning and Zoning Commission. If all information required is not provided, the Zoning Commissioner shall promptly notify the applicant of the items needed. Within twenty (20) days following the determination that the application is complete, the Planning and Zoning Commission shall meet and consider the proposed site plan and make a recommendation to the Village Council.
(Ord. 2015-09. Passed 7-13-15.)