1197.06 APPLICATION PROCEDURES.
   (a)    Pre-Application Meeting: The applicant shall attend a Pre-Application Meeting with the Village Engineer to discuss the proposed project, review the requirements of this regulation, identify unique aspects of the project that must be addressed during the review process, and establish a preliminary review and approval schedule.
   (b)    Preliminary Comprehensive Storm Water Management Plan: The applicant shall submit two (2) sets of a Preliminary Comprehensive Storm Water Management Plan (Preliminary Plan) and the applicable fees to the Village Engineer and/or the Village Administrator. The Preliminary Plan shall show the proposed property boundaries, setbacks, dedicated open space, public roads, water resources, storm water control facilities, and easements in sufficient detail and engineering analysis to allow the Village Engineer to determine if the site is laid out in a manner that meets the intent of this regulation and if the proposed storm water management practices are capable of controlling runoff from the site in compliance with this regulation. The applicant shall submit two (2) sets of the Preliminary Plan and applicable fees as follows:
      (1)    For subdivisions: In conjunction with the submission of the preliminary subdivision plan.
      (2)    For other construction projects: In conjunction with the application for a zoning permit.
      (3)    For general clearing projects: In conjunction with the application for a zoning permit.
   (c)    Final Comprehensive Storm Water Management Plan: The applicant shall submit two (2) sets of a Final Comprehensive Storm Water Management Plan (Final Plan) and the applicable fees to the Village Engineer and/or the Village Administrator in conjunction with the submittal of the final plat, improvement plans, or application for a building or zoning permit for the site. The Final Plan shall meet the requirements of Section 1197.08, shall demonstrate compliance with the Performance Standards and requirements established in Section 1197.09, and shall be approved by the Village Engineer prior to approval of the final plat and/or before issuance of a Zoning Permit.
   (d)    Review and Comment: The Village Engineer and/or the Village Administrator shall review the Preliminary and Final Plans submitted, and shall approve or return for revisions with comments and recommendations for revisions. A Preliminary or Final Plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised Preliminary or Final Plan.
   (e)    Approval Necessary: Land clearing and soil-disturbing activities shall not begin and zoning and/or building permits shall not be issued without an approved Comprehensive Storm Water Management Plan.
   (f)    Valid for Two Years: Approvals issued in accordance with this regulation shall remain valid for two (2) years from the date of approval.
(Ord. 2019-5. Passed 12-9-19.)