§ 56.28 REQUIREMENTS FOR INDIVIDUAL LOTS.
   (A)   Although no permit is required for individual lots disturbing less than one acre within a larger permitted project, a formal stormwater review shall be required prior to the issuance of an improvement location permit.
   (B)   All stormwater management measures necessary to comply with this subchapter must be implemented in accordance with the permitted plan for the larger project.
   (C)   The city requires the following surveyed information be submitted for review and approval prior to the issuance of an improvement location permit.
      (1)   Dimensions, elevations, drainage patterns and swales and location of existing buildings and natural features which are pertinent to this subchapter;
      (2)   Proposed drainage patterns;
      (3)   Location of the construction access to the site; and
      (4)   Location of perimeter erosion and sediment control measures prior to land disturbance.
   (D)   Temporary erosion prevention and sediment control measures may be removed for completion of the finish grade. Prior to removal of temporary erosion prevention and sediment control measures, permanent stabilization shall be in place a minimum of seven calendar days for sod and 45 calendar days for seed and straw.
(Ord. Z-06-09, passed 4-3-2006)