§ 56.24 PERMIT APPLICATION PROCESS.
   (A)   This SWQMP alone does not authorize or grant permission to begin development or redevelopment on subject property. It does not supersede other permits required by the city.
   (B)   All project site owners, as applicable in § 56.20(C), shall submit an application for a SWQMP on forms provided by the city.
   (C)   Applications must include a notice of intent (NOI), Perimeter Control Plan (PCP), Stormwater Pollution Prevention Plan (SWPPP) and any other necessary information or documentation requested by the city. The NOI requirements are included in division (E) of this section.
   (D)   The PCP and SWPPP are components of the SWQMP. While both plans may be approved simultaneously, the provisions of a PCP shall be implemented, inspected and accepted by the city prior to implementing the SWPPP and before other construction proceeds.
   (E)   The project site owner must notify the city and the Indiana Department of Environmental Management (IDEM) within 48 hours prior to the commencement of construction activities through the submittal of an updated NOI. Upon completion of construction activities, stabilization of the project site and removal of all temporary erosion protection and sediment control measures, the applicant shall submit a notice of termination (NOT). The city, or its designated representative, shall inspect the project site to verify that the requirements of the NOT have been met. Once the city verifies the NOT, the city will forward a copy of the verified NOT to IDEM.
      (1)   Submittal for a SWQMP application shall include a NOI letter, as required by 327 I.A.C. 15-5 and 327 I.A.C. 15-13, with proof of publication of a public notice, construction plans, a Stormwater Pollution Prevention Plan and any other necessary information or documentation requested by the city.
      (2)   The NOI letter, proof of publication of public notice and construction plans for the SWQMP shall be submitted to the city.
   (F)   The city reserves the right to require a checklist of necessary items to be completed and included with the SWQMP application submittal. Upon submittal, the SWQMP application shall be rejected in its entirety should any item on the checklist be incomplete.
(Ord. Z-06-09, passed 4-3-2006)