§ 151.023  APPLICATION PROCEDURES AND REQUIREMENTS.
   (A)   Application for such a permit shall be made, in writing, to the Floodplain Administrator on forms supplied by the borough. Such application shall contain the following:
      (1)   Name and address of applicant;
      (2)   Name and address of owner of land on which proposed construction is to occur;
      (3)   Name and address of contractor;
      (4)   Site location including address;
      (5)   Listing of other permits required;
      (6)   Brief description of proposed work and estimated cost, including a breakout of flood-related cost and the market value of the building before the flood damage occurred where appropriate; and
      (7)   A plan of the site showing the exact size and location of the proposed construction as well as any existing buildings or structures.
   (B)   If any proposed construction or development is located entirely or partially within any identified floodplain area, applicants for permits shall provide all the necessary information in sufficient detail and clarity to enable the Floodplain Administrator to determine that:
      (1)   All such proposals are consistent with the need to minimize flood damage and conform with the requirements of this and all other applicable codes and ordinances;
      (2)   All utilities and facilities, such as sewer, gas, electrical and water systems are located and constructed to minimize or eliminate flood damage;
      (3)   Adequate drainage is provided so as to reduce exposure to flood hazards;
      (4)   Structures will be anchored to prevent floatation, collapse or lateral movement;
      (5)   Building materials are flood-resistant;
      (6)   Appropriate practices that minimize flood damage have been used; and
      (7)   Electrical, heating, ventilation, plumbing, air conditioning equipment and other service facilities have been designed and located to prevent water entry or accumulation.
   (C)   Applicants shall file the following minimum information plus any other pertinent information as may be required by the Floodplain Administrator to make the above determination:
      (1)   A completed permit application form;
      (2)   A plan of the entire site, clearly and legibly drawn at a scale of one inch being equal to 100 feet or less, showing the following:
         (a)   North arrow, scale and date;
         (b)   Topographic contour lines, if available;
         (c)   The location of all existing and proposed buildings, structures and other improvements, including the location of any existing or proposed subdivision and development;
         (d)   The location of all existing streets, drives and other accessways; and
         (e)   The location of any existing bodies of water or watercourses, identified floodplain areas, and, if available, information pertaining to the floodway, and the flow of water including direction and velocities.
      (3)   Plans of all proposed buildings, structures and other improvements, drawn at suitable scale showing the following:
         (a)   The proposed lowest floor elevation of any proposed building based upon North American Vertical Datum of 1988;
         (b)   The elevation of the base flood; and
         (c)   Supplemental information as may be necessary under 34 Pa. Code, the 2009 IBC or the 2009 IRC.
      (4)   The following data and documentation:
         (a)   Detailed information concerning any proposed floodproofing measures and corresponding elevations;
         (b)   If available, information concerning flood depths, pressures, velocities, impact and uplift forces and other factors associated with a base flood; and floodway area (see § 151.046(A)), when combined with all other existing and anticipated development, will not increase the base flood elevation at any point;
         (c)   1.   A document, certified by a registered professional engineer or architect, which states that the proposed construction or development has been adequately designed to withstand the pressures, velocities, impact and uplift forces associated with the base flood.
            2.   Such statement shall include a description of the type and extent of floodproofing measures which have been incorporated into the design of the structure and/or the development.
         (d)   Detailed information needed to determine compliance with §§ 151.062(F) and 151.063, including:
            1.   The amount, location and purpose of any materials or substances referred to in §§ 151.062(F) and 151.063 which are intended to be used, produced, stored or otherwise maintained on site; and
            2.   A description of the safeguards incorporated into the design of the proposed structure to prevent leaks or spills of the dangerous materials or substances listed in § 151.063 during a base flood.
         (e)   The appropriate component of the Department of Environmental Protection’s Planning Module for Land Development; and
         (f)   Where any excavation or grading is proposed, a plan meeting the requirements of the Department of Environmental Protection to implement and maintain erosion and sedimentation control.
   (D)   Applications for permits shall be accompanied by a fee, payable to the municipality based upon the estimated cost of the proposed construction as determined by the Floodplain Administrator.