§ 50.031 PROHIBITED CONNECTIONS.
   (A)   No person shall make connection of roof downspouts, basement wall seepage or floor seepage, exterior foundation drains, areaway drains, or other surface runoff or groundwater to a building sewer or building drain which in turn is connected directly or indirectly to a public sanitary sewer. Any such connections which already exist on the effective date of this chapter shall be completely and permanently disconnected within 60 days of the effective date of this chapter. The owner(s) of any building sewers having such connections, leaks or defects shall bear all costs incidental to removal of such sources. Pipes, pumps, and pumps for such sources of ground and surface water shall be separate from wastewater facilities. Removal of such sources of water without presence of separate facilities shall be evidence of drainage to public sanitary sewer.
   (B)   All costs and expenses incidental to the installation and connection to the building sewer shall be borne by the owner(s). The owner(s) shall indemnify the city for any loss of damage that may directly or indirectly be occasioned by the installation of the building sewer. Fees for connection shall be as established by the city.
   (C)   The owner shall ensure that all excavations for building sewer installation shall be adequately guarded with barricades and lights so as to protect the public from hazard. Streets, sidewalks, parkways, and other public property disturbed in the course of the work shall be restored in a manner satisfactory to the city.
   (D)   In all buildings in which any sanitary facility drain is too low to permit gravity flow to the public sewer, sanitary sewage carried by such drain shall be lifted by an approved means and discharged to the same building sewer. Drain pipe and sump for collection of such sanitary drainage shall be above basement floor or in separately watertight or drained sump or channel.
   (E)   The building sewer shall be connected into the public sewer at the easement or property line. Where no property located service branch is available, an authorized agent of the city shall cut a neat hole into the main line of the public sewer and a suitable wye or tee saddle installed to receive the building sewer. The invert of the building sewer at such point of connection with a saddle shall be in the upper quadrant to the main line of the public sewer. A neat workmanlike connection, not extending past the inner surface of the public sewer, shall be made and the saddle made secure and watertight by encasement in epoxy cement specially prepared for this purpose. A wye and H bend fitting shall be installed at the property line between the public sewer and the building sewer. This fitting shall serve the purpose of a clean out and for applying the smoke test during inspection of the line. After testing, a cast iron or ductile iron riser will be inserted in this fitting and brought flush with the ground surface. A stopper or plug, outfitted with a type joint applicable to the pipe used, shall seal this riser against the intrusion of ground or surface water.
   (F)   All building sanitary sewer lines will be installed so as to meet or exceed the most current revision of the State Plumbing Code.
(Ord. 001-93, passed 2-1-93) Penalty, see § 50.999