§ 55.02 ENFORCEMENT ACTION AVAILABLE TO THE POTW.
   (A)   The Director of the POTW is empowered through G.S. § 143-215.6A and Chapter 52 of this code to take a wide variety of enforcement actions. The following is a list of those actions and the corresponding section of this code that describes each:
      (1)   Notice of violation: § 52.130(A);
      (2)   Consent orders: § 52.130(B);
      (3)   Show cause hearings: § 52.130(C);
      (4)   Administrative orders: § 52.130(D);
      (5)   Emergency suspensions: § 52.130(E);
      (6)   Termination of permit: § 52.130(F);
      (7)   Civil penalties: § 52.999(A);
      (8)   Injunctive relief: § 52.999(B); and
      (9)   Water supply severance: § 52.999(C).
   (B)   In addition to the actions listed above, a user who violates the provisions of G.S. § 143-215.6B may be referred by the Director to the District Attorney for possible criminal prosecution.
   (C)   In determining the amount of civil penalties for a particular violation, the Director shall consider the following factors:
      (1)   The degree and extent of the harm to the natural resources, to the public health, or to public or private property resulting from the violation;
      (2)   The duration and gravity of the violation;
      (3)   The effect on ground or surface water quantity or quality, or on air quality;
      (4)   The cost of rectifying the damage;
      (5)   The amount of money saved by noncompliance;
      (6)   Whether the violation was committed willfully or intentionally;
      (7)   The prior record of the violator in complying or failing to comply; and
      (8)   The costs of enforcement to the POTW.
   (D)   Adjudicatory hearing procedures regarding permit decisions, civil penalties and administrative orders may be found in § 52.061(H).
(Ord. passed 2-14-2022) Penalty, see § 55.99