§ 155.404 EXPIRATION OF CONCEPT PLAN.
   Once concept plan recommendations have been received from the county as provided herein, the subdivider may apply for preliminary plat approval consistent with the concept plan. If preliminary plat approval for any portion of a reviewed concept plan has not been obtained within 12 months of the date on which concept plan was accepted by the Zoning Administrator or County Commission, a resubmittal of the concept plan shall be required. One 12-month extension may be granted by the Zoning Administrator or County Commission, whichever land use authority accepted the original concept plan, if the concept subdivision proposal or the county ordinances regulating the subdivision have not changed, and if the developer applies for the extension in writing prior to the original expiration date.
(Prior Code, § 8-12-21) (Ord. 10-16, passed 12-14-2010; Ord. 19-09, passed 10-15-2019)