(A) Notice. Whenever it has been determined by the Mayor and Council that construction or repair of a sidewalk is to be ordered, they shall instruct the City Works Superintendent to notify the owner of property where the sidewalk is to be constructed or repaired of the action of the Council and that such construction or repair shall be completed within 30 days from the date of said notice.
(Prior Code, § 12.04.020)
(B) Affidavit. Upon service of a notice to a property owner to construct or repair a sidewalk, the City Works Superintendent shall file an affidavit with the City Clerk setting forth the name of the property owner upon whom the notice was served, the location of the property where the sidewalk was ordered constructed or repaired and the date of service of such notice. Upon receiving such affidavit, the City Clerk shall personally deliver or send by registered mail the affidavit to the property owner mentioned therein.
(Prior Code, § 12.04.030)
(Ord. 371, passed 8-1-1956)