§ 151.1307 FINAL PUD DEVELOPMENT PLAN REVIEW AND APPROVAL PROCESS.
   After the effective date of the approval of the PUD application and general development plan, the applicant may submit a final development plan for the total development or for sections as outlined in the approved phasing plan of the general development plan. A final development plan must be consistent with the general development plan and must be submitted within 12 months to the Community Development Director or other authorized official.
   (A)   Submittal requirements for final PUD development plan. An applicant for PUD final development plan approval shall file an application on a form provided by the city. The application shall include all the information required for a final development plan identified in Chapter 150.14 plus the following additional information:
      (1)   A project narrative describing how the final development plan is consistent with approved general development plan.
      (2)   A summary table confirming the proposed residential dwelling unit density is consistent with the approved PUD application and general development plan.
      (3)   A summary table depicting precisely the amount of common open space proposed with a designation that allows individual areas to be identified on the site plan and designates which land, if any is intended to be publicly dedicated. Land that is to remain in private ownership controlled by a property owner association or trust should be identified. Draft covenants for the property owners association or other authority must be submitted.
      (4)   A summary table identifying the precise amount and nature of any modifications from subdivision and zoning regulations that were approved as part of the general development plan approval.
      (5)   Final development plan fee as established by Council.
   (B)   Staff review and notification procedures. The final development plan will be reviewed in accordance with the review procedures for general and final development plans outlined in Chapter 150.14.
   (C)   Planning Commission review of final PUD development plan. Planning Commission shall review the final PUD development plan to determine if it is consistent with the approved PUD application and general development plan. The Commission shall review the application based on the design and conditions attached to the approved PUD application and general development plan and make written findings of fact as to whether the final development plan and conditions are consistent with the approved general development plan and associated conditions.
   (D)   Action by Planning Commission. The Planning Commission shall act on the PUD final development plan application in accordance with the procedures outlined in Chapter 150.14.
(Ord. 4-2005, passed 3-23-05)