§ 153.06 APPLICATION PROCEDURES.
   (A)   Soil-disturbing activities; submitting a Storm Water Pollution Prevention Plan or Storm Water Management Plan. The applicant shall submit three sets of the SWP3 and SWM Plan to the village as follows:
      (1)   For subdivisions. After the approval of the preliminary plans and with submittal of the improvement plans.
      (2)   For other construction projects. Thirty days prior to soil-disturbing activity.
      (3)   For general clearing projects. Thirty days prior to soil-disturbing activity.
   (B)   The Village Engineer shall review the plans submitted pursuant to division (A) of this section for conformance with current NPDES permit requirements and this chapter and approve, or return with comments and recommendations for revisions. A plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised plan. An approved SWP3 shall serve as a permit to commence soil-disturbing activities following a pre-construction meeting.
   (C)   Soil-disturbing activities shall not begin, and final plat approvals will not be issued, without an approved SWP3.
   (D)   A pre-construction meeting must be held with the Village Engineer prior to earthwork activities. The applicant, contractor, and applicant's engineer should be in attendance at the pre-construction meeting.
   (E)   A site plan for individual sublots in a subdivision may not be approved unless the larger common plan of development or sale containing the sublot is in compliance with this chapter.
   (F)   Approvals issued in accordance with this chapter shall remain valid for two years. If regulations concerning erosion and sediment control or storm water quality change prior to the beginning of active construction, a new SWP3 may be requested.
   (G)   A stop-work order may be issued by the village to suspend any soil-disturbing activity on the site until the site is in compliance with this regulation.
(Ord. 60, passed 12-5-07)