§ 1440.03 NOTIFICATION OF READINESS FOR INSPECTION.
   The owner, superintendent or contractor in charge of any building being erected or altered shall notify the Building Inspector when an excavation is made and the foundation or footing materials are on the premises, giving the location of the work and the number of the permit. No person shall build any wall or place any floor beams on said foundation until the excavation and foundation or footings are approved by the Inspector. Whenever any building has reached the point in construction where the same is ready for lath and plaster or drywall, including the complete installation of all water, steam, gas and furnace stacks and all electric wires and appliances, the owner, superintendent or contractor in charge of erecting or altering such building shall notify the Inspector that the building is ready for a lath inspection.
(Ord. 46, passed 10-11-1956)