(A) Widths. Minimum sidewalk widths shall, when installed, conform to the following standards.
Classification | Width |
Commercial areas and public building sites | 10 ft. |
Industrial areas | 5 ft. |
Multiple family area | 5 ft. |
Single family area | 5 ft. |
(B) Grades. Sidewalks shall slope one-fourth inch per foot toward the street and the profile grade shall not exceed 8%. The center line elevation of the sidewalk shall be above the corresponding street center line.
(Ord. 179, passed 2-16-78)
(A) Public utilities. Extension of water and sewer services shall be made at the discretion of the city.
(B) Water supply. Extensions of the public water supply system shall, when available, be designed so as to provide public water service to each lot.
(C) Sewage disposal. Extensions of the public sanitary sewer system shall, when available, be designed so as to provide public sewer service to each lot.
(D) Underground utilities. All telephone, electric, and gas service lines shall be placed underground within dedicated public ways or recorded easements in a manner so as not to conflict with other underground services and in accordance with community standards. All underground installation of service lines within street rights-of-way shall be completed prior to street surfacing. Upon completion of the installation of underground service lines in dedicated public ways, a tracing and two copies of plans and specifications showing the completed installation shall be filed with the Manager-Clerk.
(Ord. 179, passed 2-16-78)
(A) Utility and drainage easements. Easements of at least ten feet wide centered on rear and other lot lines as required, shall be provided for utilities where necessary. Where underground utilities are being installed, a front or side yard easement may be required. These easements shall be covered by document. Municipal water and sanitary sewer shall not constitute utilities under this section.
(B) Provided for drainage. Easements shall be provided along each side of the center line of any watercourse or drainage channel, whether or not shown on the Comprehensive Plan, to a sufficient width to provide proper maintenance and protection and to provide for storm water run-off and installation and maintenance of storm sewers.
(C) Dedication. Utility and drainage easements shall be dedicated for the required use.
(Ord. 179, passed 2-16-78)
Names of new streets shall not duplicate existing or platted street names unless a new street is a continuation of or in alignment with the existing or platted street. In that event it shall bear the same name of the existing or platted street so in alignment. Street names shall conform to the city Uniform Street Naming and Building Numbering System.
(Ord. 179, passed 2-16-78)