Section 303 - Conservation Development Design Process
   A.   The design of a Conservation Development shall follow the design process specified in Appendix C - Conservation Development Design Process. As a guide in designing Conservation Developments, applicants are encouraged to review the provisions of the Rhode Island Conservation Development Manual, RIDEM, June 2003 (as amended), in the preparation of plans. The maps illustrated in this manual provide graphic examples of what is required of applicants.
   B.   Applicants shall demonstrate to the Planning Board that this design process was considered in determining the layout of proposed streets, building locations, and open space by submitting the following items:
   (Minor and Major Subdivision/Land Development Projects)
MINOR SUBDIVISION/LAND DEVELOPMENT PROJECTS
Step
Required Item
Stage at which item must be submitted
Pre-application
Preliminary Plan
Final Plan
MINOR SUBDIVISION/LAND DEVELOPMENT PROJECTS
Step
Required Item
Stage at which item must be submitted
Pre-application
Preliminary Plan
Final Plan
1. Understanding the Site
Site Analysis Maps
T
T
2. Evaluate Site Context
Site Context Map
T
T
3. Designate Potential Conservation Areas
Potential Conservation Areas
T
T
4. Determine Maximum Number of Units
Yield formula calculation
T
5. Locate Development Areas
Sketch Plan
T
6. Locate Building Sites
Site Plan
T
T
7. Lay out Streets, Trails, and Other Infrastructure
Infrastructure & Utilities Plan
T
T
8. Design and Program Open Space
Open Space Plan
T
T
9. Draw in Lot Lines
Site Plan
T
T
10. Establish Ownership and Management of Open Space
Open Space Management Plan
T
T
 
MAJOR SUBDIVISION/ LAND DEVELOPMENT PROJECTS
Step
Required Item
Stage at which item must be submitted
Pre-application
Master Plan
Preliminary Plan
Final Plan
MAJOR SUBDIVISION/ LAND DEVELOPMENT PROJECTS
Step
Required Item
Stage at which item must be submitted
Pre-application
Master Plan
Preliminary Plan
Final Plan
1. Understanding the Site
Site Analysis Maps
T
T
2. Evaluate Site Context
Site Context Map
T
T
3. Designate Potential Conservation Areas
Potential Conservation Areas
T
T
T
4. Determine Maximum Number of Units
Yield formula calculation
T
5. Locate Development Areas
Sketch Plan
T
T
6. Locate Building Sites
Site Plan
T
T
T
7. Lay out Streets, Trails, and Other Infrastructure
Infrastructure & Utilities Plan
T
T
8. Design and Program Open Space
Open Space Plan
T
T
9. Draw in Lot Lines
Site Plan
T
T
10. Establish Ownership and Management of Open Space
Open Space Management Plan
T
T