SECTION 15.503.  ISSUANCE OF ZONING CERTIFICATE.
   A.   A zoning certificate shall be either issued or refused by the Zoning Administrator within fourteen (14) days after the receipt of an application therefor, or within such further period as may be agreed to by the applicant; provided, however, that the Zoning Administrator shall have a period of twenty-two (22) days within which to issue or refuse a zoning certificate on all applications which are required to comply with the provisions of this Article.
   B.   When the Zoning Administrator refuses to issue a zoning certificate, he shall advise the applicant in writing of the reasons for the refusal.
   C.   A zoning certificate shall become null and void six (6) months after the date on which it is issued unless, within such six (6) month period, construction, moving, remodeling, or reconstruction of a structure is commenced or a use is commenced.
(Ord. 397, passed 5-12-99)