§ 7.90.310 ISSUANCE OF BUILDING PERMITS.
   (A)   Building permits may be issued for a site graded under an approved plan and valid grading permit upon completion, inspection, approval of precise grade, and inspection as required by this chapter. Only building permits for construction of model homes may be issued prior to completion of rough grading for the site, provided that rough grading is completed and inspected for the model home sites.
   (B)   Building permits shall not be issued for a site graded under a rough grading permit until a new precise grading plan is approved, a grading permit issued, and the provisions noted above are satisfied.
   (C)   No building permit shall be issued unless and until all conditions of approval have been satisfied to the satisfaction of the approving authority.
(Ord. 2022-364, passed 11-16-2022)