§ 7.90.150 HAUL ROUTES FOR EARTH MATERIAL.
   (A)   The City Engineer/Public Works Director may specify the route for moving any earth materials over public streets, whether or not the destination site or origination site of the earth materials is subject to a grading permit. The City Engineer/Public Works Director may further specify load limits where, in his or her opinion, the standard load capacity of vehicles used in such hauling would cause excessive damage to streets on the designated route. Any specified route or load limit shall be made in writing and a copy shall be provided to the Engineering Department. Deviation from the designated route or load limits shall constitute a violation of this chapter.
   (B)   The holder of a haul route permit shall be responsible for maintaining public rights-of-way used for hauling in a condition free of dust, earth material, or debris discharged or released during or attributable to the haul trips to/from the grading operation.
   (C)   Any person moving earth materials in violation of this chapter shall be financially responsible for any damage to the public streets and shall pay to the city the cost, as determined by the
City Engineer/Public Works Director, of repairing such damage or shall repair the damage to the satisfaction of the City Engineer/Public Works Director.
   (D)   At least 24 hours before the moving of earth materials is to commence, the applicant shall notify the City of Menifee Engineering Department.
(Ord. 2022-364, passed 11-16-2022)