9-3-3: PERFORMANCE BOND; IMPROVEMENT REQUIREMENTS:
Before a building moving permit shall be issued providing for the moving of a building, house or structure to a location within the corporate limits of the city, the applicant must provide the city with a performance bond in form satisfactory to the city guaranteeing that the applicant will promptly complete construction of the house, building, or structure so moved so that the same will meet all of the provisions of the city building code as well as any other applicable ordinances of the city. Such performance bond shall be in an amount equal to one hundred fifty percent (150%) of the cost as determined by the city code enforcement officer necessary to cover the construction of such improvements. The improvements of said building, house or structure shall include, but shall not be limited to, the following:
   A.   Painting: Painting all exterior walls, doors and door frames, windows and window frames as required by the city code enforcement officer.
   B.   Roofing: Install or cause to be installed new roofing whenever, in the opinion of the city code enforcement officer, the existing roof is unsightly, dilapidated or leaking.
   C.   Gutters: Construct, install or cause to be installed adequate roof gutters and downspouts upon such building, house or structure.
   D.   Grading And Sodding: Install or cause to be installed a finish grade on all parts of the premises onto which such building, house or structure is moved including the planting or installation of live sodding on all parts of the plot or parcel involved.
   E.   Landscaping: Install or cause to be installed proper landscaping upon the premises onto which such building, house or structure is moved of a type and nature comparable to the landscaping in the immediate neighborhood of the lot or property to which such building, house or structure is moved.
   F.   Drainage: Construct and provide all necessary and proper drainage upon the property upon which such building, house or structure is to be situated in accordance with a plan submitted by the applicant and approved by the city code enforcement officer.
   G.   General Construction: Update and improve all plumbing, heating and electrical equipment to meet then current specifications as set forth in the city building code as well as other applicable ordinances. (1981 Code 501 § 5)