(A) The Building Official or his or her designee shall keep complete records of all permits issued and inspections made and other official work performed under the provisions of this chapter.
(B) When the Electrical Inspector condemns all or part of any electrical installation, the owner or his or her agent may within five days after receiving written notice from the electrical inspector, file a petition in writing for review of said action of the Electrical Inspector with the Electrical Examining and Appeals Board. Upon receipt of the petition, the Board shall at once proceed to determine whether said electrical installation complies with this chapter, and within five working days shall make a decision in accordance with its findings.
(Ord. 122, passed 3-21-1995)