(A) Upon the completion of the wiring of any building, it shall be the duty of the person, firm or corporation installing the same to notify the Building Department, who shall notify the Electrical Inspector(s) to inspect the installation within 72 hours/three working days and if it is found to be fully in compliance with this chapter and does not constitute a hazard to life and property, he or she shall issue, upon request, to such person, firm or corporation for delivery to the owner a certificate of inspection.
(B) All wires which are to be hidden from view shall be inspected before concealment and any person, firm or corporation installing such wires shall notify the City Building Department, giving sufficient time in which to make the required inspection before such wires are concealed. At least 72 hours/three working days will be considered as sufficient notice.
(Ord. 122, passed 3-21-1995) Penalty, see § 155.99