10-1-4: PERMIT FEES ESTABLISHED; PENALTY FEE:
The following fees shall be charged for permits required by this chapter:
Type Of Construction/Project
Fees
Type Of Construction/Project
Fees
A. Residential Construction:
 
 
1. a. New construction (single-family, 2-family, multi-family)
$0.25/sq. ft.
 
 
Plus plumbing review/inspection fees:
 
 
 
 
Single-family dwelling
$112.00
 
 
 
2-family or multi-family dwelling
$84.00/unit plus $28.00/building
 
b. Additions
$0.25/sq. ft. ($50.00 minimum fee)
 
 
Plus plumbing review/inspection fee
$56.00
 
 
Plus fee per plumbing fixture
1.50/fixture
 
c. Remodeling
$0.25/sq. ft. ($50.00 minimum fee)
 
 
Plus plumbing review/inspection fee
$56.00
 
 
Plus fee per plumbing fixture
1.50/fixture
 
d. Minor permit extension (any permit other than subsection A1a, A1b or A1c of this section):
 
 
 
6 month extension
1-1/2 times the original building permit fee
 
Major permit extension (any permit as referenced in subsection A1a, A1b or A1c of this section):
 
 
 
6 month extension
1/2 the cost of the original building permit fee
 
 
1 year extension
Cost of the original building permit fee
 
2. Air conditioning
$40.00
 
3. Antenna/satellite dish
30.00
 
4. Backflow prevention installation
50.00
 
5. Deck
$30.00 plus $0.05/sq. ft.
 
6. Demolition of principal building on premises
$100.00
 
7. Door replacement
25.00
 
8. Driveway
25.00
 
9. Electrical installation/upgrade
50.00
 
10. Fence
25.00
 
11. Fireplace
50.00
 
12. Furnace (changing source or new unit)
35.00
 
13. Gazebo
$30.00 plus $0.05/sq. ft.
 
14. Garage
$ 0.15/sq. ft.
 
15. Lawn sprinkler system
50.00
 
16. Pools and hot tubs:
 
 
a. Aboveground
60.00
 
b. In ground
115.00
 
c. Hot tub
35.00
 
d. Storable swimming pool
30.00
 
17. Raising, shoring or underpinning of structures
15.00
 
18. Re-roof
25.00
 
19. Sewer repair
25.00
 
20. Shed
30.00
 
21. Siding
25.00
 
22. Stone, brick veneer
37.50
 
23. Water repair
25.00
 
24. Window replacement
25.00
 
25. Minimum fee for all new residential construction, including miscellaneous construction unless otherwise specified
22.50
 
26. Temporary Certificate of Occupancy
50.00
 
27. Plan review fee: new construction/addition/alteration
80.00
 
28. Water heater replacement
35.00
 
29. All private walks that have steps and stoops
25.00
 
30. Retaining walls over 4 feet in height
25.00
B. Nonresidential Construction:
 
 
1. a. New construction:
 
 
 
First 200 sq. ft.
250.00
 
 
201 sq. ft. - 20,000 sq. ft.
0.08/sq. ft.
 
 
20,001 sq. ft. and above
0.05/sq. ft.
 
 
Plus plumbing review/inspection fee
215.00
 
 
Plus fee per plumbing fixture
1.50/fixture
 
b. Additions:
$0.25/sq. ft. ($50.00 minimum fee; $10,000.00 maximum fee)
 
 
Plus plumbing review/inspection fee
$86.00
 
 
Plus fee per plumbing fixture
1.50/fixture
 
c. Remodeling:
$0.25/sq. ft. ($50.00 minimum fee)
 
 
Plus plumbing review/inspection fee
$86.00
 
 
Plus fee per plumbing fixture
1.50/fixture
 
d. Minor permit extension (any permit other than subsection B1a, B1b or B1c of this section):
 
 
 
6 month extension
1-1/2 times the original building permit fee
 
Major permit extension (any permit referenced in subsection B1a, B1b and B1c of this section)
 
 
 
6 month extension
1/2 the cost of the original building permit fee
 
 
1 year extension
Cost of the original building permit fee
 
2. Accessory structure (garage, shed, etc.)
$0.15/sq. ft. ($50.00 minimum fee)
 
3. Air conditioning, central
$ 75.00
 
4. Antenna/satellite dish
60.00
 
5. Awning/canopy
50.00
 
6. Backflow prevention installation
50.00
 
7. Deck
65.00
 
8. Demolition
200.00
 
9. Door replacement
50.00
 
10. Driveway
45.00
 
11. Electrical installation/upgrade
110.00
 
12. Elevator
120.00
 
13. Fence
35.00
 
14. Fire protection/sprinkler system
200.00
 
15. Furnace (new unit only)
75.00
 
16. Gazebo
65.00
 
17. Incinerator/crematory
50.00
 
18. Irrigation/lawn sprinkler system
60.00
 
19. Parking lot
45.00
 
20. Raising, shoring, underpinning structure
200.00
 
21. Re-roof
75.00
 
22. Sewer repair
75.00
 
23. Siding
50.00
 
24. Signs:
 
 
a. Nonilluminated
50.00
 
b. Illuminated
55.00
 
c. Portable/temporary
$30.00 fee plus $30.00 deposit1. Following the expiration of the portable/temporary sign permit to whom the permit was issued must contact the Community and Economic Development Department, during normal business hours (8:00 A.M. to 5:00 P.M. Monday through Friday, excluding recognized holidays which the office is not open), at (815)363-2170, within 5 business days to schedule an inspection to verify its removal. If the sign has been removed, the permit will be closed and the $30.00 deposit will be refunded to the applicant. If the applicant does not contact the Community and Economic Development Department within 5 business days following the expiration of the portable/temporary sign permit, the deposit will be permanently retained by the City.
 
25. Site development permit
$ 50.00
 
26. Stone, brick veneer
37.50
 
27. Water repair
75.00
 
28. Window replacement
50.00
 
29. Temporary Certificate of Occupancy
100.00
 
30. Certificate of Occupancy
0.00
 
31. Plan review fee for new construction/addition/alteration
$0.00/$50.00/$200.00
 
32. Minimum fee for all new nonresidential construction unless otherwise specified herein
$45.00
 
33. Water heater replacement
35.00
 
34. Seal coating of all nonresidential parking lots
45.00
 
35. All private walks that have steps and stoops
45.00
 
36. Retaining walls over 4 feet in height
25.00
 
37. Dumpster enclosures nonresidential only
35.00
C. Reinspection fees:
 
 
1. Plumbing - residential
28.00
 
Plumbing - nonresidential
43.00
 
2. All others (after second failed inspection)
37.50
 
Note:
   1.    A portable/temporary $100.00 deposit shall be required exclusively for grand opening signs. Grand opening signs must comply with all other provisions outlined in subsection B24c of this section, in addition to all regulations included in section 10-20-13, “New Business Grand Opening Signs”, of this title.
   D.   Increase Due To Construction Prior To Permit: The aforesaid residential and nonresidential permit fees shall be increased by fifty percent (50%) where construction has been commenced before a permit is issued for such work.
   E.   Collection And Deposit: All fees as are herein established or made, by amendment, or hereinafter established by the City Council, shall be collected by the Community Development Department and deposited with the Finance Director.