(A) Permit required for:
(1) Demolition of a primary or secondary structure;
(2) Demolition of any structure with a foundation.
(B) Conditions for permit issuance:
(1) Occupancy permit is revoked for the property;
(2) No remaining accessory structure is permitted to be used for any purpose if the primary structure has been demolished or lost due to a natural catastrophe. A demolition permit must be obtained within one year unless a zoning permit is issued for a new primary structure in that same time period.
(C) Shut off of all utilities shall be coordinated with appropriate agency.
(Ord. O-2019-24, passed 9-9-2019)