§ 178.187 TEMPORARY USES - CONSTRUCTION.
   Soil shredding, batch plants, logging, and other resource preparation or harvesting shall be permitted per the following:
   (A)   Site.
      (1)   On site. Processing must occur on the construction site.
      (2)   Original to site. Only materials original to the site may be processed.
   (B)   Duration. The length of processing time shall be the duration of the project unless the Planning Commission sets a shorter time period. In no instance shall the processing continue for more than two years without approval from the Planning Commission and Village Council.
(Ord. O-2019-24, passed 9-9-2019)