9.7.032: VEGETATION AND REVEGETATION:
   (A)   The developer shall submit a slope stabilization and revegetation plan which shall include a complete description of the existing vegetation, the vegetation to be removed and the method of disposal, the vegetation to be planted and slope stabilization measures to be installed. The plan shall include an analysis of the environmental effects of such operations, including the effects on slope stability, soil erosion, water quality and fish and wildlife.
   (B)   Vegetation sufficient to stabilize the soil shall be established on all disturbed areas as each stage of grading is completed. Areas not contained within lot boundaries shall be protected with perennial vegetal cover. After all construction is completed, efforts shall be made to plant those species that tend to recover from fire damage and do not contribute to a rapid rate of fire spread.
   (C)   The developer shall be fully responsible for any destruction of native vegetation proposed for retention. He shall carry the responsibility both for his own employees and for all subcontractors from the first day of construction until the notice of completion is filed. The developer shall be responsible for replacing such destroyed vegetation. (Ord. 822, 2-23-2006, eff. 3-16-2006)