9.6.10: CONSTRUCTION DRAWINGS AND AS BUILT INFORMATION:
A full set of as built (record) drawings of all improvements intended for public use and maintenance, including, but not limited to, water and sewer lines, and including also private and public streets, shall be furnished to the city for the permanent records of the city within sixty (60) days of completion of the construction. (Ord. 822, 2-23-2006, eff. 3-16-2006)
Such drawings shall take the form of regular construction drawings at one hundred (100) scale with detail at ten (10) scale. In addition, a digital file according to the digital data submittal standards policy, written to an appropriate media, in AutoCAD® compatible format (or other electronic format specified by the city) containing all drawing information, shall accompany the drawings. The warranty period for utilities, streets and other improvements shall not begin until as builts are delivered and acknowledged by the city. (Ord. 899, 5-24-2012)