9.6.09: INSPECTION AND INITIATION OF WARRANTY PERIOD:
   (A)   The owner and/or developer shall retain a full time licensed professional engineer or licensed construction manager who shall supervise the construction inspection and certify that all improvements were constructed in accordance with the approved drawings and city standards.
   (B)   A three (3) year warranty period for public infrastructure constructed and accepted for maintenance by the city shall commence when a final walkover is conducted and written acceptance of the utilities by the city is completed. Final walkover and acceptance shall include the following items:
      1.   Inspection of utility systems and review of test data furnished by the developer.
      2.   Review of site cleanliness and serviceability of street and drainage system.
      3.   Evidence that lot or property pins are in place. (Ord. 822, 2-23-2006, eff. 3-16-2006)