§ 154.073 SEQUENCE OF CONSTRUCTION.
   (A)   All underground utilities, sanitary sewers, storm sewers and water mains installed in streets, alleys, service roads or highways shall be constructed or installed prior to the surfacing of the streets. Service connections to the underground utilities and sewers shall be extended to two feet beyond the property line of each lot so as to obviate disturbing the surface improvements in the public ways when service connections are later made.
   (B)   All excavations below subgrade of proposed pavements shall be made by drilling or open cut. If done by open cut, granular trench backfill conforming to the latest issue of the Standard Specifications for Road and Bridge Construction of the State Department of Transportation shall be used.
   (C)   All excavations below the subgrade of existing pavements shall be made only by drilling under the existing pavement in such a way that surfacing is not disturbed or weakened.
(2000 Code, § 155.063) (Ord. 876, passed 8-4-1975) Penalty, see § 154.999