§ 154.022 FEES.
   (A)   Filing fee.
      (1)   The following non-refundable filing fee shall be collected from the applicant at the time of application for site plan review or preliminary plat review for any commercial, industrial, institutional or multi-family development, whether they be new construction or remodeling.
 
0 to less than 3 acres
$1,000
3 to less than 10 acres
$2,500
10 to less than 35 acres
$5,000
35 to less than 50 acres
$8,000
50 or more acres
$15,000
 
      (2)   The filing fee amount shall be deducted from the total of the final engineering review fee and the inspection fees as outlined in divisions (B) and (C) below, and required to be paid in full at the time of recording of the subdivision plat or issuance of a building permit, whichever comes first.
   (B)   Final engineering review. At the time of application for approval of the final engineering site improvement plans, the developer shall pay a fee sufficient to compensate the Village Engineer and/or his or her designee for examination of the final engineering plans and all supporting documents in the amount of 2% of the design engineer’s estimate of cost of the entire project.
   (C)   Inspection of project improvements. All improvements approved by the Village Engineer and/or his or her designee shall be inspected during the course of construction by the Village Engineer and/or his or her designee. As compensation for such inspection, the developer shall pay an inspection fee in the amount of 3% of the design engineer’s estimate of cost of the entire project. Said inspection fee shall be in addition to the final engineering review fee.
   (D)   Cost of recording. At the time of receiving approval of a final plat, the subdivider shall pay a fee sufficient to cover the cost of recording.
(2000 Code, § 155.017) (Ord. 876, passed 8-4-1975; Ord. 1905, passed 4-21-2003)