§ 153.38 INSPECTIONS.
   (A)   (1)   The Director of Community Development or the Village Engineer shall make inspections as hereinafter required and shall either approve that portion of the work completed or shall notify the permittee wherein the work fails to comply with the site development or erosion and sedimentation control plan as approved. Plans for grading, stripping, excavating and filling work bearing the stamp of approval of the Director of Community Development shall be maintained at the site during progress of the work.
      (2)   In order to obtain inspections, the permittee shall notify the Director of Community Development at least two full working days before the completion of:
         (a)   Stripping and clearing;
         (b)   Rough grading;
         (c)   Final grading; and
         (d)   Final landscaping.
   (B)   If stripping, clearing, grading or landscaping are to be done in phases or areas, the permittee shall give notice and request inspection at the completion of each of the above work stages in each phase or area. If an inspection is not made and notification of the results given within five working days after notice is received by the village from the permittee, the permittee may continue work at his or her own risk, without presuming acceptance by the village. Notification of the results of the inspection shall be given in writing at the site.
(2000 Code, § 154.38) (Ord. 1141, passed 5-17-1982)