§ 153.20 REVIEW AND APPROVAL.
   (A)   Each application for a site development permit shall be reviewed and acted upon according to the following procedures.
      (1)   (a)   The Director of Community Development, with the approval of the Village Engineer, will review each application for a site development permit to determine its conformance with the provisions of this chapter. The Director of Community Development may also refer any application to the Will-South Cook County Soil and Water Conservation District or any other local government or public agency within whose jurisdiction the site is located for review and comment.
         (b)   Within 30 days after receiving an application, the Director of Community Development shall in writing, do the following:
            1.   Approve the permit application if it is found to be in conformance with the provisions of this chapter, and issue the permit;
            2.   Approve the permit application subject to such reasonable conditions as may be necessary to secure substantially the objectives of this chapter, and issue the permit subject to these conditions; or
            3.   Disapprove the permit application, indicating the deficiencies and the procedure for submitting a revised application or submission.
      (2)   No site development permit shall be issued for an intended development site unless:
         (a)   The development, including, but not limited to, subdivisions and planned unit development, has been approved by the village where applicable;
         (b)   Such permit is accompanied by or combined with a valid building permit issued by the village; or
         (c)   The proposed earth moving is coordinated with any overall development program previously approved by the village for the area in which the site is situated.
   (B)   Failure of the Director of Community Development to act on an original or revised application within 30 days of receipt shall constitute denial of the application unless the time is extended by agreement between the Director of Community Development and the applicant. Pending preparation and approval of a revised plan, development activities shall be allowed to proceed in accordance with conditions established by the Director of Community Development with the approval of the Village Engineer.
(2000 Code, § 154.20) (Ord. 1141, passed 5-17-1982)