(a) After a building or other structure, or any part thereof, has been demolished or moved, all sanitary sewers that served such building or other structure, or any part thereof, must be plugged at or near the lot line with concrete. Such plugging must be inspected and approved by the Sewer Department before it is covered and a permit for this work must be obtained from the Sewer Department.
(b) A basement cavity may be filled with noncombustible material to a level two feet below existing ground level as noted in (c) below.
(c) All basement walls shall be reduced to two feet below existing ground level.
(d) From two feet below existing ground level to four inches above existing ground level, the basement cavity shall be filled with clean fill.
(Ord. 46-1989. Passed 3-20-89.)