1313.18 FINAL INSPECTION.
   The holder of an electrical installation permit shall notify the Building Department when the entire installation of wiring and equipment has been completed, and it shall make inspection of the completed job within seventy two hours, excluding Sundays and legal holidays, from such notification. If the installation passes inspection, the Inspector shall stamp on the building permit the fact that he has passed the work. If the installation shall not pass inspection, the Inspector shall notify the permit holder of any violation and such permit holder shall correct such violations within ten days from the date of the written notice.
(Ord. 153-2010. Passed 12-20-10.)