§ 152.41 CONSTRUCTION SITE STORM WATER POLLUTION PREVENTION PLAN.
   (A)   Activities that are applicable to this chapter, per § 152.03, must provide a construction site storm water pollution prevention plan (CSSPPP).
   (B)   The construction site storm water pollution prevention plan may be a full sized plan sheet with necessary notes for requirements or may be a narrative explaining construction site operating procedures to minimize or eliminate storm water pollution as a result of construction activities.
   (C)   The items covered in a CSSPPP are dependent on the activities and the materials required on site to complete the project. Therefore, the detail of the Plan may be more or less depending on the site activities planned. Standard items that shall be in a CSSPPP include but are not limited to the following:
      (1)   Purpose;
      (2)   Construction site description;
      (3)   Activities/materials to be addressed in the CSSPPP;
      (4)   Construction site operating procedures;
      (5)   Activities/materials monitoring & maintenance; and
      (6)   Emergency and spill procedures.
   (D)   Should construction site activities/materials change during construction, the CSSPPP must reflect the changes. Therefore, the plan must be kept on-site at all times and shall be amended as necessary with the approval of the Inspector. Should major changes be warranted, a revised plan must be submitted for review and approval.
(Ord. 2007-33, passed 6-20-07)