§ 156.129 FAILURE TO INITIATE CONSTRUCTION AFTER FINAL DEVELOPMENT PLAN APPROVAL.
   (A)   Period of validity. No approval of a final development plan shall be valid for a period longer than two years from the date of approval unless within such period a building permit is obtained and construction of a development’s foundation is commenced.
   (B)   Extension. The Board of Trustees may grant a one year extension upon written request of the original applicant if the application submitted is substantially the same as the initially-approved application.
(`92 Code, § 40-5-20) (Ord. 00-11, passed 7-5-00)